Business

Grid Delays Push Renewable Sector to Seek ₹3,000 Cr Relief

Published: 7 August 2026 · 1 min read

What Happened

RE developers have approached the central government for a relief package of up to ₹3,000 crore after delays in key transmission infrastructure severely restricted power evacuation from commissioned projects. Delays in substations such as Neemrana-II and Bikaner-III in Rajasthan have reportedly forced some projects to operate at just 10-20% of their capacity, leading to significant revenue losses and debt-servicing challenges.

Key Takeaways

Around 21 GW of RE capacity is awaiting dedicated transmission connectivity, with nearly 12 GW facing evacuation constraints, highlighting a growing gap between renewable capacity additions and transmission infrastructure development.

Sources

Economic Times, Indian Express